HYDE PARKWAY CONSTRUCTION
August 30, 2010 -
DDS Contractors, working for NYSEG, is nearing completion of their
gas-replacement project. Sidewalks should be completed this week
followed by driveway apron and lawn restorations, which should
complete the project.
July 25, 2010 - DDS Contractors, working for NYSEG, has installed the new 6” gas main under the east side from Main to Foster. Tie-ins are still necessary at Main and Jackson intersections. For the next 2 weeks they will continue to install new individual gas services from the new main to each home. After that they intend to start sidewalk, lawn and driveway restorations. If you have any questions about NYSEG’s project there is a NYSEG inspector who is on the job each day. May 27, 2010 - Last year the Palmyra Highway Department completed a street reconstruction project between Main Street and Jackson Street. Every year I update our local NYSEG gas contact on the street projects that we have on the horizon. For the two years leading up to this Hyde Parkway street project we had been in discussions with NYSEG about a gas main replacement. As the residents on Hyde Parkway know, NYSEG was hoping to get easements along the east side for their new main, however, they were unsuccessful. As a result, I recently learned that starting sometime in the next couple weeks, they will be installing a new gas main directly underneath the sidewalk on the east side of the street from Main Street to Foster Street. I understand there will be no impacts to the recently paved section of Hyde Parkway, but open cuts will be necessary on Jackson Street and Foster Street to tie-in their mains. As a result of the Canandaigua Street detour this summer onto Hyde Parkway, we will be pushing off our street project for the stretch between Jackson and Foster another year, but there will be a new sidewalk along the entire east side of the street which is needed. |
|
©2010 Town & Village of Palmyra, NY. All
rights reserved. |
||